Construction Timeline
Interactive Gantt chart showing construction phases, dependencies, and milestones
Total Duration
108 days
~16 weeks
Current Phase
3/8
Wall Construction
Progress
32%
Day 35 of 108
Est. Completion
73
days remaining
Construction Phases
Timeline showing all phases, dependencies, and current progress
Day 0Day 20Day 40Day 60Day 80Day 100
Site Preparation
7 days
Today
7d
Land clearing, surveying, and foundation excavation
Excavator, Survey team, 2 laborers
Foundation & Plinth
14 days
14d
Concrete foundation, DPC, and plinth beam construction
Mason, 4 laborers, Concrete mixer
Wall Construction
21 days
21d
Brick/block laying for all walls up to roof level
2 masons, 6 laborers, Scaffolding
Roofing
10 days
10d
Roof trusses, sheeting, and waterproofing
Carpenter, Roofer, 4 laborers
Plumbing & Electrical
14 days
14d
First fix plumbing, electrical conduits, and RPM infrastructure
Plumber, Electrician, 2 laborers
Plastering & Rendering
14 days
14d
Internal and external wall plastering
2 plasterers, 4 laborers
Finishes & Fixtures
21 days
21d
Flooring, painting, doors, windows, and fixtures
Painter, Carpenter, Tiler, 4 laborers
Final Inspection & Handover
7 days
7d
RPM equipment installation, testing, and final inspection
RPM technician, Inspector
Key Milestones
Important checkpoints throughout construction
Site Preparation
- Site cleared
- Foundation marked
Foundation & Plinth
- Foundation poured
- DPC installed
- Plinth complete
Wall Construction
- Walls to window level
- Walls to roof level
Roofing
- Trusses installed
- Sheeting complete
- Waterproofing done
Plumbing & Electrical
- Pipes installed
- Conduits laid
- RPM hub wiring complete
Plastering & Rendering
- Internal plastering done
- External rendering complete
Finishes & Fixtures
- Flooring complete
- Painting done
- Fixtures installed
Final Inspection & Handover
- Medical devices installed
- System tested
- Certificate issued